Proposals are being brought forward for a new link road in Warrington, referred to as the Warrington Western Link.
The Warrington Western Link will ease congestion and improve traffic flow in the Borough. Warrington Borough Council wants to improve the town for local residents and businesses. Our plans for the Warrington Western Link will improve the quality of life for residents in the Borough.
Before a planning application is submitted, we want to engage with local people to make them aware of the current proposals. Visit the virtual exhibition to find out more about the proposed Western Link and how to have your say.
Watch the video below to hear your questions being answered by the project team.
Warrington Western Link
Project Milestones
Procure specialist external consultants and contractors to support the project
Early 2020
Public Engagement
Late 2020
Cabinet approval for securing statutory powers for the schem
Mid 2021
Submission of planning application
May 2021
Working up detailed designs
2021/22
Securing necessary approvals
Mid 2022
Completion of Full Business Case/Securing of Full Approval – Submission to DfT and securing their approval
Late 2022
Start of scheme construction
Early 2023
Completion of scheme construction
Early 2026
Project close out and evaluation
2026/27
Thank you for taking the time to visit the Warrington Western Link Website.
The public engagement period has now closed. You can still visit the pages of this website to learn more about the plans for the Warrington Western Link road.